The activation of WIP calculation occurs only if ‘Project Posting Categories’ have been configured, which we will enter in the project’s general area. Entering the category will automatically populate the field at the WBS line level as well.
Project Posting Categories
This is a standard setup, for more information: https://learn.microsoft.com/en-us/dynamics365/business-central/projects-how-setup-jobs?tabs=current-experience
Others important setup are WIP Method and WIP Posting Method:
The method encoding allows you to specify the timing for recognizing costs and revenues, giving you the flexibility to manage the two pieces of information differently.
IMPORTANT:the app only supports the 2 methods circled in orange: ‘JOB COMPLETED’ and ‘PERCCOMPL’.
Note: The last column distinguishes between system-defined methods and those that can be custom-defined. Obviously, the rows with this flag are not modifiable.
This is a standard setup, for more information: https://learn.microsoft.com/en-us/dynamics365/business-central/projects-understanding-wip
Specifies how to recording WIP:
On the WBS rows, it is necessary to insert 2 informations:
Total WIP can assume the following values: