MPS, MRP planned execution with Job queue

It is possible to plan the execution of MPS, MRP and the distribution of reports by applying some criteria and filters.

In Planning Setups (MPL), you can set up different setup configurations for the system to perform planning calculations.


After inserting several configuration lines, it is also possible to make them run according to a specific sequence, for example:

  • MPS and production items only

  • MPS and purchase items only

  • MRP for production items only

  • MRP for purchase items only


Tab General

FieldDescription
Code, Descriptionset a code and description for the setup line
Scheduledestablish if the setup is to be scheduled
Schedule Sequenceif the setup is scheduled, set the phase of the planning sequence

Tab Planning

FieldDescription
Worksheet Template Namechoose the template name
Journal Batch Nameselect a batch on which the entries will be posted
Delete Worksheet Lineswhen planning starts, choose whether to delete the lines in the corresponding worksheet
MPS, MRPchoose if you want to calculate the MPS and / or the MRP
Starting Date Formula / Ending Date Formulaenter a formula for the planning start / end date
Use Forecastyou can use a forecast made previously
Exclude Forecast Beforeset a date before which you want to exclude the schedule
Respect Param. on Exceptionchoose whether to respect these parameters

Action Message

FieldDescription
Planning Worksheet Template / Nameit is possible to define a Planning template and name on which the calculation is to be distributed
Item Filterit is possible to filter by item (eg all items with “Prod. Order” supply system)
Work Center Filter / Requisition Filterit is also possible to filter by work center / requisition

Through Related-> Calculate planning it is possible to execute the planning as set up and it is also possible to calculate the material status .